Precautions Before Testing The Universal Crusher

1. Check the quality of the raw materials required for the testing machine: whether the particle size is uniform, the size of the water content in the material, and whether there are impurities.
2. Check whether it is suitable for the grinding process requirements of the testing machine material, whether the quality of the installed casing and lining plate is reliable, and whether it can achieve uniformity when fed into the testing machine.
3. Start the lubricating oil pump, observe whether the ammeter swings normally, whether the screw runs smoothly, and prepare everything to feed normally again.
4. When entering the initial formal feeding stage, it is required to be small and uniform. Observe the changes and operation of various ammeters, remove impurities on the surface of mineral raw materials, gradually increase the amount of material until everything is normal, maintain a certain gap, adjust the operating speed of various tasks, record the discharge amount and particle size under various conditions. When a higher yield of material can be obtained, normal crushing operation can be carried out. Generally speaking, during the feeding test, we cannot be less than 2 hours.

 

1

 

Send Inquiry

whatsapp

Phone

VK

Inquiry